During the demolition phase of the rooftop construction project, it was discovered that some of the steel beams under the concrete had been exposed to moisture and had begun to rust. Because of this, it was determined that the beams needed to be replaced.
The new beams are being delivered on Wednesday, August 3rd. The first phase of the delivery will begin at approximately 8:30 p.m. with the assembly of a crane that will close both of the eastbound lanes of Hollywood Boulevard in front of Body Energy and Pie Hole.
The completion of the delivery and the demobilization of the crane will last until the very early hours of the morning and it could be very loud. The timing of the delivery was dictated by the Los Angeles Department of Transportation.
Should you have any questions about this, or anything to do with the ongoing construction project, please stop by the management office on the third floor.