Category: Manager’s Messages

  • Rooftop Demolition 4/6 & Master Alarm to Sound 4/7

    A commencement date for the major demolition phase of the rooftop construction project has been confirmed. The major demolition will begin on Wednesday, April 6th at approximately 9:00 a.m. This phase of the project is estimated to take between twelve and fifteen days to complete. Noise and vibrations from jackhammering will be felt on the…

  • Governing Document Revision Ballots

    The governing document revision ballots have been mailed out to all homeowners. The official date they were mailed out by Association Balloting was Friday, March 18, 2022. You will receive one ballot for every unit that you own. If you have yet to receive your ballot(s), please contact management immediately as they’re due by the…

  • Jackhammer Testing – 3/23/22

    The major demolition phase of the rooftop reconstruction project is approaching very quickly. On Wednesday, March 23rd, jackhammer testing will be performed on the rooftop beginning at approximately 12:00 p.m. The idea behind the testing is to see what type of jackhammer would be best to use to attempt to mitigate the amount of noise…

  • 37th Los Angeles Marathon – 3/20/22

    The 37th running of the Los Angeles Marathon will take place on Sunday, March 20th. The marathon begins at Dodger Stadium early in the morning and ends at the Santa Monica Pier. Part of the course passes directly through Hollywood and causes several road closures. While the marathon is in progress, there will be times…

  • Construction Update

    The major demolition portion of the project is to begin within the next seven days. This includes a lot of jackhammering which will cause noise and vibrations to carry through units on the higher floors. The jackhammering is estimated to take a minimum of four weeks to complete. If you work from home and the…

  • Temporary Gym Now Open

    As a result of the rooftop construction, a temporary gym is now open for everyone to use. The gym is located on the third floor, in the garage area next to the management office. There’s one treadmill, one elliptical, two bicycles, dumbbells, weight benches, medicine balls, and a few other items for your use. To…

  • Rooftop Construction to Begin – 1/24/22

    The much anticipated rooftop construction project will begin on January 24, 2022. The scope of work at the beginning of the project will be concrete deck saw cutting, demoing of concrete for exploratory work, and planter excavation. With construction beginning on January 24th, this will be the last weekend when you will be able to…

  • Rooftop Construction

    For those of you that have been away from Broadway Hollywood, the first steps of the rooftop construction have begun. Scaffolding has been built along Vine Street and Hollywood Boulevard for the protection of pedestrians during the demolition phase of the project. Scaffolding has also been constructed on one of the buildings southern facing balconies…

  • Water Shut Off Notice

    On Tuesday, December 21, 2021, all units will experience an interruption in their hot and cold water service. The interruption is required to perform plumbing upgrades / replacements, and will last from approximately 9:00 a.m. to 5:00 p.m. Should you have any questions or concerns, please don’t hesitate to contact management.

  • Rooftop Social & Construction Town Hall Meeting

    On Thursday, December 2nd, you’re invited to the rooftop to meet the architects and contractors that will be performing the repairs for the rooftop reconstruction project. The Town Hall meeting will begin at 6:00 p.m. with a short presentation of what to expect during the construction. This will be followed by a Q&A so the…